SOURCES SOUGHT
99 -- Maintenance Dredging of Mattituck Harbor, New York, Federal Navigation Channel
- Notice Date
- 11/20/2023 1:13:17 PM
- Notice Type
- Sources Sought
- Contracting Office
- W2SD ENDIST NEW YORK NEW YORK NY 10278-0004 USA
- ZIP Code
- 10278-0004
- Solicitation Number
- W912DS24S0012
- Response Due
- 12/5/2023 11:00:00 AM
- Archive Date
- 12/20/2023
- Point of Contact
- Nicole C. Fauntleroy, Phone: 9177906139
- E-Mail Address
-
nicole.fauntleroy@usace.army.mil
(nicole.fauntleroy@usace.army.mil)
- Description
- Background Information� The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of the Mattituck Harbor, New York Federal Navigation Channel. �The dredged material would be dredged and subsequently transported to and placed at an upland placement site at a contractor furnished, state permit upland placement site. The proposed maintenance dredging would remove approximately 11,500 cubic yards of selected critical shoals from the silty/clay areas in the Mattituck Harbor. Dredging would be required to a depth of -7 feet Mean Lower Low Water (MLLW) plus 1 feet of allowable overdepth. �The dredged material is expected to consist primarily of silt/clay. It is recommended that the proposed work only be performed by utilizing a mechanical dredge with a clamshell bucket. �Additionally, multiple, ocean-going barges and tug boats will be needed to perform the work during the dredging, transport and unloading operations. �The dredged material would be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the dredging and placement sites are located. � The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing and final placement of the dredged material for the upland placement portion of the project, and shall submit evidence of such permits and approvals to the government. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 1,500 cubic yards per calendar day for the dredging, transportation, and final placement of the material. �The presence of dredging equipment in the channel will impact ship traffic and it is necessary to maintain this production rate while minimizing the duration of this impact. The proposed work is anticipated to take place between September and December 2024. �The work is estimated to cost between $1,000,000.00 and $5,000,000.00. SURVEY OF THE DREDGING INDUSTRY The following confidential survey questionnaire is designed to apprise the Corps of prospective dredging contractors� project execution capabilities. Please provide your response to the following questions. All questions are regarding to the Mattituck Harbor, NY maintenance dredging project.� General� 1)�� �Have you ever worked on dredging jobs similar in nature to this project? If so, please describe the project and for whom the work was performed. Identify a point of contact and phone number, as a reference of relevant experience.� 2)�� �Do you have experience with the placement of dredged material at a contractor-furnished, state permitted, upland placement site? Please list your experience. 3)�� �What percentage of work (volume of material dredged, transported, and ultimately placed) can you perform with your own equipment or equipment owned by another small dredging contractor? 4)�� �Have you performed dredging within the north shore of Long Island? 5)�� �Would you be willing to bid on the project described? If the answer is no, please explain why not.� 6)�� �Would you be bidding on this project as a sole contractor, prime contractor with subcontractor(s) or as a joint venture?� 7)�� �Is there a dollar limit on the size of contract that you would bid? If so, what is that limit? 8)�� �What is the largest dredging contract, in dollars, on which you were the prime contractor?� 9)�� �What is your bonding capacity per contract? What is your total bonding capacity?� 10)�� �Do you have experience using the USACE Resident Management System (RMS 3.0) for delivering Submittals, Daily Dredging reports and Pay Estimates? 11)�� �Do you have experience applying the USACE EM 385-1-1 (Nov 2014) and all requirements? Deficiencies observed on site will require immediate attention and action to meet all applicable safety codes. � Equipment 12)�� �What type of dredge equipment do you own and / or operate that is suitable for the work described? �Do you own a clamshell bucket? �Please list each piece of equipment capable of performing each type of work described, i.e., dredging, transfer, transportation, and final placement of the material. �For each dredge that you list, please specify its bucket size(s), and any other pertinent characteristics.� 13)�� �Do you own material scows? If so, how many do you have available for use? Please list the name of the scow, its type (ocean-going, bottom dump, etc.) and the capacity.� 14)�� �Will you be able to meet a production rate of 1,500 cubic yards per calendar day with placement at a contractor furnished, state permitted upland placement site(s)? 15)�� �Do you have experience with the use of an automated Dredged Material Monitoring System (Black Box/Silent Inspector) or employing a Dredged Material Inspector (DMI)?� �
- Web Link
-
SAM.gov Permalink
(https://sam.gov/opp/ca5df8195d1a43a8b94177ef750b20c1/view)
- Place of Performance
- Address: Mattituck, NY, USA
- Country: USA
- Country: USA
- Record
- SN06890871-F 20231122/231120230053 (samdaily.us)
- Source
-
SAM.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's SAM Daily Index Page |