SOLICITATION NOTICE
F -- Wiley Hall Dean's office, Reception office, Deans bathroom and hallway corridor
- Notice Date
- 7/31/2025 12:42:06 PM
- Notice Type
- Combined Synopsis/Solicitation
- NAICS
- 562910
— Remediation Services
- Contracting Office
- 6923G2 DOT MARITIME ADMINISTRATION KINGS POINT NY 11024 USA
- ZIP Code
- 11024
- Solicitation Number
- 6923G225Q000011
- Response Due
- 8/6/2025 6:00:00 AM
- Archive Date
- 08/21/2025
- Point of Contact
- CARMEN I. FELIZ, Phone: 5167266149, Fax: 5167735131, Amit S. Narine, Phone: 5167266032
- E-Mail Address
-
FELIZC@USMMA.EDU, NarineA@usmma.edu
(FELIZC@USMMA.EDU, NarineA@usmma.edu)
- Small Business Set-Aside
- SBA Total Small Business Set-Aside (FAR 19.5)
- Description
- The purpose of this modification is to respond request for information as well as extend the date and time of offer due as follows: a. Offers submission due date is hereby extended to August 6th, 2025 @0900. b. Response to request for information posted on attachment A contractor shall provide a New York and/or Environmental Protection Agency (EPA) qualified and licensed lead abatement specialist to provide all management, tools, supplies, notification(s), equipment and labor necessary to perform lead abatement at Wiley Halls Dean, Reception Offices, Deans Bathroom and Hall #4 in accordance with all federal, state and local laws and regulations. See SOW for additional details. Statement of Work (SOW) Wiley Hall 2?? Deck Dean & Reception Offices Lead Paint Abatement / Remediation 1. Description of Services A contractor shall provide a New York and/or Environmental Protection Agency (EPA) qualified and licensed lead abatement specialist to provide all management, tools, supplies, notification(s), equipment and labor necessary to perform lead abatement at Wiley Hall�s Dean, Reception Offices, Dean�s Bathroom and Hall #4 in accordance with all federal, state and local laws and regulations. 2. General Requirements a. Abatement and disposal shall be in accordance with all federal, state and local laws and regulations including but not limited to requirements established by 40 CFR Part 745, EPA (Renovation, Repair, and Painting (RRP) Rule), D.O.T. (49 C.F.R. � 173), and RCRA. b. The contractor shall possess and provide current proof of all federal, state and local trainings, license(s) and certification(s) including but not limited to the RRP, be registered with the EPA and be licensed as a lead abatement contractor through either New York and/or EPA. c. The contractor shall submit a �Occupant Protection Plan� to the Contracting Officer Representative (COR), Public Safety Department, and Department of Public Works (DPW). d. The designated work area(s) must be sealed from neighboring occupied areas of the Quarter/academy with the appropriate barriers (i.e., plastic) and hazard notifications (warning signs) per federal, state and local laws and regulations throughout the duration of the project until final clearance has been achieved. e. All work must be completed using wet methods per federal, state and local laws and regulations. f. Apply a lead encapsulation paint or primer, over all surfaces to be painted, in accordance with manufacturer�s instructions. The contractor shall use an EPA approved lead encapsulant and provide SDS for all products used throughout the project. g. Given the sensitive nature of these areas (occupied resident), USMMA is requiring all work to be done in a negative pressure enclosure to minimize impact to building occupants and operations. h. All work must be completed using HEPA vacuum with a minimum filter requirement capable of capturing particulates of 0.3 microns with 99.97% efficiency and in conjunction with all federal, state and local laws and regulations. i. Throughout the duration of the abatement/remediation project, the work area(s) must be contained until a formal lead clearance is completed. USMMA�s contracted hygienist shall be on-site to conduct oversight of the lead abatement process, perform air monitoring, and the final lead clearance. The clearance levels for dust wipes per the EPA�s Hazard Standards and Clearance Levels for Lead in Paint, Dust and Soil requirements are as followed: a. 10 ug/ft2 � floors b. 100 ug/ft2 � window sills and troughs j. All work and clearances must be coordinated with the USMMA�s MARAD, COR, Public Safety Department, DPW and contracted IH. If clearance levels are not achieved in accordance with federal, state and local laws and regulations, the contractor shall perform an environmental re-cleaning and undergo another lead clearance process at no additional cost incurred to the government. If required, this process will be repeated until acceptable levels are achieved in accordance with all federal, state and local laws and regulations. k. The work area must be cordoned off per federal and state laws and regulations with clearly visible barriers (i.e., caution tape) where only authorized and trained individuals related to the abatement project may enter. l. Establish a containment area in accordance with federal and state laws and regulations, to fully separate the work area from other areas of the building. Maintain and identify emergency exit(s) from the work area or establish alternate exit(s) compliant with all federal, state and local laws and regulations. m. The contractor will ensure academy occupants are protected at all times and prevent any potential lead and/or lead dust contamination in accordance with all federal, state and local laws and regulations. n. All electrical equipment shall be run through Ground Fault Interrupt Circuit (GFCI) throughout the course of the project. o. The contractor shall be responsible for installation and connection of all temporary utilities required to complete the abatement. The contractor shall ensure all electrical equipment run through Ground Fault Interrupt Circuit (GFCI) throughout the duration of the project. DPW personnel will show the contractor where to connect to water and power. The contractor shall provide and install temporary GFCI panels for electrical service. p. The contractor shall secure infrastructure equipment (i.e., HVAC system) and all other relevant equipment to prevent contamination in neighboring areas per federal, state and local laws and regulations. q. Provide accurate and complete waste manifest(s) for lead disposal in accordance with all federal, state and local laws and regulations. r. Provide copies of all federal, state and local notifications. s. Provide accurate records of abatement completion. 3. Additional Notes a. Start Date: To be determined (Upon USMMA Contracting Officer�s (CO) award of contract). Completion Date: 4 days after award of contract. The completion date includes but is not limited to the submittal process, performance of the work, final air clearance, inspection, waste disposal and waste manifest delivery. b. A full work plan must be prepared in advance and submitted to the COR, Public Safety, DPW, and contracted IH for approval. The plan must be approved at least two (2) business days prior to commencement of work. c. All work must be scheduled with the COR at least 48 hours prior to commencement. d. The academy must be immediately notified of any service and/or activity interruptions. Any potential unforeseen interruptions or issues must be immediately related to the COR, Public Safety Department, and DPW. e. A pre-bid onsite walkthrough with the DPW, COR, and Public Safety Department will be conducted to identify and mark the proposed area where removal / abatement will take place. The contractor will become familiar with on-sight conditions and restrictions. The square footage identified in the SOW are approximations and will need to be assessed and verified by the contractor during the walkthrough and incorporated into the bid submission. The contractor is responsible for verifying quantities and locations where all work is to be performed. Failure to do so shall not relieve the contractor of its obligation to furnish all labor and materials necessary to perform the work. f. All work including but not limited to on-site assessment(s) and document review(s), must be completed between normal business hours of operation (7am � 4pm), Monday � Friday, unless additional approval is granted by the CO and COR. g. Any debris generated during abatement activities will be removed by the contractor daily from the affected area(s) and academy premises. Area(s) will be left neat and clean daily and after work is completed, suitable for all normal academy activities. 3 h. Contractor must properly dispose of waste in accordance with all RCRA requirements. Documentation of this disposal shall be provided to the COR and Public Safety. i. The contractor will be required to abate (remove) the paint materials from the indicated areas. If the paint cannot be removed while still leaving a clean, smooth and paintable surface, the contractor will be required to remove building material (i.e. wood pieces) in its entirety for the selected areas and replace with similar material that meet all regulatory and industry standards. j. Square Footage of removal areas include: � Dean�s Office (207): ~ 399 SF � Reception�s Office (206): ~ 378 SF � Dean�s Bathroom (207A): ~76 SF � Hall #4 (208B): ~25 SF These areas will be outlined at the time of the on-site walkthrough. Abatement shall occur to include removal of the selected areas and outlining materials (i.e., paint or marker). k. The contractor shall assume full responsibility and liability for compliance with all applicable federal, state and local regulations related to any and all aspects of the project. l. The contractor is responsible for ensuring client satisfaction throughout the duration of the project. Any discrepancies, issues and concerns identified by the client originating from the contractor will be addressed, documented and corrected in a timely manner. Note: The contractor is responsible for any subcontractors that may be used throughout this project. Subcontractors are required to adhere to all the requirements set forth within this SOW. 4 4. Images of Area of Concern Dean�s Office (207): ~ 399 SF Reception�s Office (206): ~ 378 SF Dean�s Bathroom (207A): ~76 SF Hall #4 (208B): ~25 PLEASE SEE ATTACHED SITE PICTURES
- Web Link
-
SAM.gov Permalink
(https://sam.gov/opp/b20c9bdfadfe449ba8cfe675b46df978/view)
- Place of Performance
- Address: Kings Point, NY 11024, USA
- Zip Code: 11024
- Country: USA
- Zip Code: 11024
- Record
- SN07531622-F 20250802/250801000104 (samdaily.us)
- Source
-
SAM.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's SAM Daily Index Page |